28 October 2010
Medgaz: Long history, long delay
Medgaz has been driven more by the visions of the two governments than by an immediate commercial need
FOR A project costing €0.9bn ($1.2bn) and with such a long history, there seems to have been little hurry in sending the first gas through Medgaz. When the final investment decision was taken, at the end of 2006, start-up was targeted for the first half of 2009. The target slipped to the end of that year, then to September this year, and now to year-end. Delays were attributed to unspecified technical problems, although laying work was completed on-schedule at the end of 2008. Saipem carried out the technically demanding construction of the 24-inch offshore pipeline, running 210 km from Béni Saf, Algeria, to Almería. The firm's Castoro Sei laid the shallow-water parts of the line, working o
Also in this section
24 December 2025
As activity in the US Gulf has stagnated at a lower level, the government is taking steps to encourage fresh exploration and bolster field development work
23 December 2025
The new government has brought stability and security to the country, with the door now open to international investment
23 December 2025
A third wave of LNG supply is coming, and with it a likely oversupply of the fuel by 2028
22 December 2025
Weakening climate resolve in the developed world and rapidly growing demand in developing countries means peak oil is still a long way away






