28 October 2010
Medgaz: Long history, long delay
Medgaz has been driven more by the visions of the two governments than by an immediate commercial need
FOR A project costing €0.9bn ($1.2bn) and with such a long history, there seems to have been little hurry in sending the first gas through Medgaz. When the final investment decision was taken, at the end of 2006, start-up was targeted for the first half of 2009. The target slipped to the end of that year, then to September this year, and now to year-end. Delays were attributed to unspecified technical problems, although laying work was completed on-schedule at the end of 2008. Saipem carried out the technically demanding construction of the 24-inch offshore pipeline, running 210 km from Béni Saf, Algeria, to Almería. The firm's Castoro Sei laid the shallow-water parts of the line, working o
Also in this section
2 April 2026
Alongside a rapid continued build-out of renewables, China’s latest five-year plan stresses the value of domestic hydrocarbon production for energy security and calls for increased Russian gas imports
2 April 2026
The government is taking important steps to revive domestic production, lift investment and benefit from the geopolitical crisis even if more needs to be done in the longer term
1 April 2026
Golden Pass’s startup offers QatarEnergy a timely boost but may also force a difficult choice between honouring disrupted contracts and capitalising on soaring spot LNG prices
1 April 2026
It is not a case of if or when, but the length and magnitude of economic damage from elevated oil prices






