28 October 2010
Medgaz: Long history, long delay
Medgaz has been driven more by the visions of the two governments than by an immediate commercial need
FOR A project costing €0.9bn ($1.2bn) and with such a long history, there seems to have been little hurry in sending the first gas through Medgaz. When the final investment decision was taken, at the end of 2006, start-up was targeted for the first half of 2009. The target slipped to the end of that year, then to September this year, and now to year-end. Delays were attributed to unspecified technical problems, although laying work was completed on-schedule at the end of 2008. Saipem carried out the technically demanding construction of the 24-inch offshore pipeline, running 210 km from Béni Saf, Algeria, to Almería. The firm's Castoro Sei laid the shallow-water parts of the line, working o
Also in this section
23 April 2026
The addition of an oil pipeline to the Power of Siberia 2 gas project could ensure deliveries of Russian oil to China, materially shorten logistics lines between West Siberia and final customers, and—amid disruption in the Strait of Hormuz—offer a land-based export route that reduces exposure to maritime chokepoints
23 April 2026
There is a clear push to bolster exports to Asia amid uncertainty around its North American neighbour, but there are limits to the benefits from the energy crisis
23 April 2026
Shell made the play-opening discovery in Namibia’s Orange basin back in 2022, but its next well could decide whether the project can actually be commercialised
22 April 2026
The failure of OMV Petrom’s keenly watched exploration campaign at Bulgaria’s Han Asparuh block highlights the Black Sea’s uneven track record, despite major successes like Neptun Deep and Sakarya






