Countdown to Mozambique LNG restart
Mozambique’s insurgency continues, but the security situation near the LNG site has significantly improved, with TotalEnergies aiming to lift its force majeure within months
TotalEnergies is aiming to lift its four-year-old force majeure on the $20b Mozambique LNG project in the coming months amid improved security conditions. However, the French major is first seeking a freeze on engineering, procurement and construction (EPC) costs. Given the prolonged delay, the project’s overall cost could increase by up to 15% above the original estimate at the time of FID in June 2019. Operations at Mozambique LNG were suspended in April 2021 when TotalEnergies declared force majeure and withdrew all personnel from the site in Afungi, located in Cabo Delgado province, northeastern Mozambique. The decision followed an incursion by Islamist insurgents into the nearby town of
Also in this section
6 February 2026
The long close relationship between key supplier Qatar and pivotal buyer Japan becomes even deeper following new landmark deal
6 February 2026
Partnerships across the LNG value chain have evolved over time, growing in both complexity and importance, according to panellists at LNG2026
6 February 2026
Nigeria's mega-refinery is still trying to solve many challenges, all while its owner talks up expansion
5 February 2026
While broadly supportive of EU efforts to tackle methane emissions, representatives of the gas industry warn it could deter supply contracting if timelines and compliance requirements are not made more pragmatic






